Main Modifications Consultation

Ends on 7th September 2026 (28 days remaining)

Chapter 7. Economy

MM44 Comment

Page 117

Para/Table/Box/Policy

Para 7.5

Proposed Modification

Amend paragraph to read:

The Local Plan should ensure that a sufficient quantity of land is available for employment generating uses and development in Rutland throughout the plan period. These are uses falling within Class E c) to g) (commercial, business and service), Class B2 (general industrial) and Class B8 (storage and distribution) of the Town and Country Planning (Use Classes) Order 1987 (as amended). Where the term employment development is used in Policy E1 below, the definition of this term is the same as that defined above for employment use.

In respect of other employment uses, mentioned below in Policy E1, are thosethat do not fall within the primary employment use classes E c)-g), B2 or B8, but which nevertheless generate employment or contribute to economic activity.

Reason

To provide clarity and consistency of terminology regarding other employment uses by referring to use classes E c-g and replacing ‘other employment generating uses’ with ‘other employment uses’

MM45 Comment

Page 117

Para/Table/Box/Policy

Para 7.7

Proposed Modification

Delete paragraph 7.7:

St George’s Barracks and Woolfox are proposed as Future Opportunity Areas (policy SS4) within this Local Plan. These sites may deliver new employment premises and uses in the future; however, the sites are not included within the employment land allocations below.

Reason

Consequence of deleting SS4

MM46 Comment

Page 117

Para/Table/Box/Policy

E1

Proposed Modification

Amend policy text to read:

Policy E1 - Strategic employment land allocations

The following sites are proposed as strategic employment development sites. The employment generating use(s) considered most appropriate for each site is indicated, together with the gross site area. Sites areas are also shown on the Policies Map.

E1.1 Car Park 3 Rutland Showground, Oakham

High quality office and other high-quality employment

E class uses c) and g) only, ensuring a majority of floorspace is delivered for offices

3.0ha

E1.2 Uppingham Gate, Uppingham

Range of employment uses

6.8ha

E1.3 Burley Appliances Ltd, Oakham

Industrial

1.0ha

E1.4 1.2 Land at Pit Lane Ketton

Light industrial uses

E(g)(iii) - Light Industrial and B2

0.9ha

E1.51.3 Woolfox Depot, Great North Road

Industrial B2, nonstrategic B8 (units under 100,000 sq ft) and E(g)

8.219.11ha

E1.61.4 Land at Wireless Hill, South Luffenham

Industrial

B8 – Storage and Distribution

6.5ha

E1.5 Land West of Bosal Way, Barleythorpe

Class E(g) ii – Research and Development and iii – Light Industrial, B2, B8

1.8ha

Permission may also be granted for other employment generating uses on these sites where the following criteria are satisfied:

Reason

For consistency and clarity:

  • To ensure the allocate use aligns with the Use Class Order (Council’s hearing statement, paragraph 79)
  • To ensure allocation at Woolfox reflects planning permission 2025/0130/OUT
  • To remove sites E1.2 and E1.3 as allocations due to their current status (NP allocation and residential planning permission granted, respectively)
  • To include existing employment allocation

MM47 Comment

Page 118

Para/Table/Box/Policy

E1

Proposed Modification

Amend policy text to read:

  1. the proposed use will generate new employment opportunities and will achieve economic investment and growth of the County;
  2.  it is demonstrated that the proposed scheme will make a significant contribution to the local economy through the generation of a range of additional jobs;
  1. 3)the alternative use would not have a detrimental impact on the overall supply and quality of employment land within the County;
  2. 4)an end user for the proposed development has been positively identified; and/or
  3. 5)on sites of 1ha or greater demonstrate through an economic impact assessment that the proposed scheme will create significant employment requiring NVQ level 4 or above and/or apprenticeships leading to NVQ level 5 and above.

Reason

To improve clarity, remove ambiguity, and ensure stronger, more consistent protection of allocated employment land by requiring all tests to be met rather than allowing partial compliance.x`

MM48 Comment

Page 118

Para/Table/Box/Policy

E1

Proposed Modification

Insert additional paragraph into policy under new clause 3) to read:

Development proposals which would result in the loss or reduction of land allocated under Policy E1 for employment purposes will only be supported where it is demonstrated that such development would not undermine the overall supply of employment land in the County and is otherwise justified, having regard to relevant policies of this Plan.

Reason

To ensure consistency with the approach taken in Policy E3, providing clearer criteria and a more robust framework to resist unjustified loss of employment land, supporting the evidence that such land is important to the local economy

MM49 Comment

Page 118

Para/Table/Box/Policy

E1.1

Proposed Modification

Amend policy text to read:

Policy E1.1 Car Park Rutland Showground

Policy E1.1

Car Park 3 Rutland Showground

OPUS ID: 130

Site area: 3ha

Allocated use: High quality office and other high-quality employmentE class uses c) and g) only, ensuring a majority of floorspace is delivered for offices

The proposed development should be designed to incorporate the following key principles within the layout:...

Reason

For clarity and consistency :

  • To clarify E use classes for site E1.1 Car Park 3 Rutland Showground,Oakham, with majority of the site for office use.
  • To ensure consistent wording across all similar policies.

MM50 Comment

Page 119

Para/Table/Box/Policy

E1.2

Proposed Modification

Delete the whole of Policy E1.2 Uppingham Gate

Reason

Site allocated in Uppingham Neighbourhood Plan.

RCC49, 2.40

MM51 Comment

Page 120

Para/Table/Box/Policy

E1.3

Proposed Modification

Delete the whole of Policy E1.3 Burley Appliances

Reason

Site now has planning permission for an alternative use

RCC49, 2.41

MM52 Comment

Page 120

Para/Table/Box/Policy

E1.4

Proposed Modification

Amend policy text to read:

E1.4 1.2 Pit Lane, Ketton

Policy E1.41.2

Pit Lane, Ketton

OPUS ID: 4508

Site area: 1ha

Allocated use: Light Industrial uses. E(g)(iii) - Light Industrial and B2

The proposed development should be designed to incorporate the following key principles within the layout:

For Information:

An application for this site should be accompanied by the following evidence/surveys........ :

  • Heritage Impact Assessment.

Reason

For clarity and consistency with other policies and to include the expectation that proposed developments will be additionally accompanied by a heritage impact assessment.

MM53 Comment

Page 121

Para/Table/Box/Policy

E1.5

Proposed Modification

Amend policy text to read:

E1.5 1.3 Woolfox Depot, Great North Road

Policy E1.51.3

Woolfox Depot, Great North Road

OPUS ID: 8033

Site area: 8.2 19.11ha

Allocated use: Light Industrial B2, non-strategic B8 (units under 100,000 sq ft) and E(g)

The proposed development should be designed to incorporate the following key principles within the layout:

  1. Provide access to new units from a new roundabout on Great North Road, including a dedicated new access arm serving the Zeeco site via the existing access point adjacent to the existing Zeeco business, off Great North Road
  2. Ensure any development on the site does not impact on the Mineral Safeguarding Area in accordance with Policy MIN3

Reason

For clarity and consistency:

  • Change use/area/access for Woolfox Depot, criterion c) in accordance with granted permission.
  • To ensure consistency with other allocation policies by removing 'within the layout'.
  • To ensure consistency with amendments made to other policies relating to the reference to the Mineral Safeguarding Area and Policy MIN3

MM54 Comment

Page 123

Para/Table/Box/Policy

E1.6

Proposed Modification

Amend policy text to read:

E1.6 1.4 Wireless Hill, South Luffenham

Policy E1.61.4

Wireless Hill, South Luffenham

OPUS ID: 6605

Site area: 6.5ha

Allocated use: B8 – Storage and Distribution

The proposed development should be designed to incorporate the following key principles within the layout:

  1. Retain the existing tree belts on the existing Wireless Hill Industrial Estate’s northeast boundary and northwest boundaries, if possible, recognising the likely need to provide site access points in these locations;
  2. Provide visual screening in the form of trees along the site’s northeast and northwest boundaries
  3. Include measures to reduce the amount of artificial light required on site and to limit the impact of light spillage from the site
  4. Ensure that access to the site via the existing access point on Wireless Hill can be achieved, including any necessary improvement works.
  5. Ensure the size and massing of the units mirror those on the existing Wireless Hill site to limit the development’s impact on the landscape
  6. Make appropriate provision for surface water management systems, including a SUDS drainage system taking the site’s location within a Groundwater Source Protection Zone
  7. Ensure any development of the site does not impact on the Mineral Safeguarding Area in accordance with Policy MIN3
  8. Provide Consider, where possible, enhancements to pedestrian infrastructure to South Luffenham to encourage sustainable travel.
    1. Provide mitigation, where appropriate, as determined by the findings of the Transport Assessment, to ensure the safety of the railway crossing on Station Road’

For Information:

  • Full transport assessment – including considerationsof the need for pedestrian connectivity and associated infrastructure for South Luffenhamas well as the safety of railway crossing.

Reason

For clarity and consistency and:

  • to allow flexibility in considering the need for improvements to pedestrian infrastructure
  • to recognise that access points are likely to breach the tree belts
  • to ensure railway crossing safety
  • to ensure consistency with amendments made to other policies relating to the reference to the Mineral Safeguarding Area and Policy MIN3

MM55 Comment

Page 123

Para/Table/Box/Policy

Proposed Modification

Insert new Policy E1.5 to read:

E1.5 Land West of Bosal Way, Barleythorpe

Policy E1.5

Land West of Bosal Way, Barleythorpe

No OPUS ID

Site area 1.8ha

Allocated use: Class E(g) ii and iii, B2, B8

The proposed development should be designed to incorporate the following key principles:

  1. Deliver highquality employment floorspace suitable for a mix of uses including Class E(g)ii, B2 and B8, whilst ensuring a major any of floorspace is delivered for office use and any other uses on the site are justified, compliment the allocated use, and are appropriate and required for the operation of the site
  2. Ensure the layout, scale, form and design of development respects the character of the surrounding area and minimises impacts on visual and residential amenity, including where proposals involve external storage, storage racking up to the approved heights, plant areas or servicing yards located near residential boundaries.
  3. Provide appropriate access and infrastructure, including safe and suitable vehicular access arrangements, servicing and turning areas, and pedestrian and cycle connectivity that integrates with the surrounding network.
  4. Allow for flexibility in unit sizes and configurations to accommodate a range of employment uses and operational requirements.
  5. Make appropriate provision for surface water management, incorporating sustainable drainage systems (SuDS) in accordance with the drainage hierarchy.
  6. Ensure development takes account of existing water and wastewater infrastructure within and adjacent to the site.
  7. Retain and protect existing trees and hedgerows, including those protected by Tree Preservation Order 2020/0002/TPO, and ensure development is designed and constructed in accordance with BS5837, avoiding incursion into Root Protection Areas.
  8. Incorporate measures to minimise noise, disturbance and light spill, including through the siting and orientation of buildings, servicing areas and fixed plant, to protect the amenity of nearby residential properties.
  9. Protect and enhance biodiversity, including any Local Wildlife Sites on or adjacent to the site, through the retention and enhancement of existing habitats and the incorporation of appropriate ecological enhancement measures.

For Information

An application for this site should be accompanied by the following evidence/surveys which include, where appropriate, evidence that the necessary mitigation measures have been planned into the design and layout of the development:

  • Transport Assessment and Travel Plan
  • Drainage Strategy, including SuDS design and maintenance arrangements
  • Flood Risk Assessment
  • Foul drainage strategy, informed by engagement with Anglian Water
  • Ecological Assessment, including consideration of Local Wildlife Sites, biodiversity net gain information and longterm management proposals
  • Arboricultural Impact Assessment, including Tree Protection Plan, with specific reference to Tree Preservation Order 2020/0002/TPO
  • Noise Impact Assessment
  • Lighting Strategy
  • Archaeological Assessment
  • Ground Investigation Report
  • Construction Environmental Management Plan (CEMP)

Reason

Inclusion of the remainder of an existing Local Plan employment allocation and to provide development principles for the new allocation in line with the provisions made for other allocation policies in the Plan.

MM56 Comment

Page 124

Para/Table/Box/Policy

E2

Proposed Modification

Insert text into the Policy after the clauses to read:

For the purposes of Policy E2, “employment uses” includes development within Use Class E(c) to E(g) and Use Classes B2 and B8 of the Town and Country Planning (Use Classes) Order (as amended). This reflects the range of uses typically appropriate within the Planned Limits of Development, including offices, research and development, light industrial uses, general industrial uses, and storage and distribution. In this context the terms ‘employment uses’ and ‘employment development’ have the same definition as set out above.

Insert supporting text after Policy E2 to read:

Why are these policies needed?

Policy E1 is intended not only to support the delivery of employment development, but also to safeguard allocated employment sites for their intended purpose over the Plan period. Where alternative or nonemployment uses are proposed on allocated employment land, the Council will carefully consider the implications for the longterm supply of employment land and the delivery of the economic strategy set out in this Plan.

The inclusion of a reference to the relevant use classes in Policy E2 is intended to provide greater precision in how the policy is applied, ensuring that proposals are assessed consistently against the types of employment uses anticipated by the Plan. This supports effective decisionmaking by aligning the operation of Policy E2 with the range of employment activities envisaged within the Economy chapter, while retaining flexibility for appropriate employment development on unallocated sites.

Reason

To improve clarity for applicants and decision‑makers by explicitly defining the types of uses covered by the policy, aligning with the updated Use Classes Order and ensuring consistency across the Local Plan.

MM57 Comment

Page 124

Para/Table/Box/Policy

E2 – supporting text

Proposed Modification

Amend existing paragraphs 7.15 to 7.17 to read:

Employment Needs

The Employment Needs & Economic Development Study recommends the following:

  • office requirement for 7,450 sqm or 1.5Ha
  • industrial and warehousing need for between 18.2 ha and 34.9 ha, giving a combined employment land requirement of between 19.7ha and 36.4ha, wWith an acceptable mid-point of 26.6 ha be planned for in the Local Plan
  • With an acceptable mid-point of 26.6 ha be planned for in the Local Plan need to acknowledge the wider ‘roaming’ demand on the A1 corridor that could support a large development with a logistics focus

The study identifies that this combined requirement of 19.7ha - 36.4ha could support the total jobs that can be supported in the County based on the identified need range from 3,335 to 4,378 additional jobs. For completion, it is recommended that the mid-point of 26.6 ha is reasonable to plan for and this would result in 3,860 additional jobs based on the assumptions used in the Study. However, it concludes that while a range of job creation is possible with the recommended level of need, the link between floorspace growth and jobs growth cannot be wholly reconciled. This is particularly the case for industrial jobs which comprises the greater percentage of the need.

The Employment Needs & Economic Development Report (2023) also considered the suitability of existing employment allocations and new sites which had been proposed to the Council for employment uses to meet future needs. Site allocations have also been assessed against the Council’s site assessment criteria to ensure that they are suitable for development.

Employment Land Supply

The table below sets out the contribution all sources of employment land make to the overall supply in meeting the employment land requirement established in Policy E1. Policy E1 identifies allocations to deliver a minimum level of employment land over the plan period alongside existing completions and commitments. For completions and commitments this supply includes only land genuinely capable of accommodating employment floorspace. For Woolfox (Policy E1.3), this is of particular relevance where the planning and allocation boundary covers 19.11ha. However, this includes substantial area required to deliver biodiversity net gain, with the net developable area reduced down to 12ha. This is included in the commitments figure below.

Table 5: Sources of employment land supply

Source of supply

Gross (ha)

Commitments*

15.97

Completions 21-25

6.41

Local Plan Allocations**

11.3

Neighbourhood Plan Allocations

2.6

Total

36.28

*All allocations with planning permission are counted here

** Includes Land at Bosal Way, which is remaining land from previous Local Plan allocation

The total employment land supply from all sources totals 36.28 ha. This sits within the combined requirement range of 19.7–36.4 ha identified and provides appropriate headroom over the 26.6 ha midpoint requirement. This ensures that the Plan not only meets anticipated employment land needs but also provides flexibility to accommodate market variation and supports the level of job growth identified.

Reason

Additional detail of employment supply to be added to supporting text. To include table detailing supply from each source, including completions and commitments and a total of all sources, based on gross site area figures. Explanation should also be provided for Woolfox where a smaller boundary and resultant site area has been used.

MM58 Comment

Page 127

Para/Table/Box/Policy

E3 (above paragraph 7.22)

Proposed Modification

Amend the title preceding Policy E3 to read:

Employment Development within the Planned Limits of Development

Reason

To ensure the heading accurately reflects the following text and policies

MM59 Comment

Page 127

Para/Table/Box/Policy

Policy E3 – supporting text

Proposed Modification

Amend paragraph 7.23 to read:

The policy seeks to provide flexibility for employment uses of land and the needs of enterprise. It sets out the Council’s requirements for applications for a change of use from employment to other uses including housing. The policy will offer a range of employment opportunities across the County within the built-up areas to accommodate the expansion of local businesses and to ensure that there are opportunities for companies to move into the area. This policy should be read alongside Policies E4 and E10, which set out the detailed development management and site specific considerations for employment development proposals.

Reason

To improve clarity and highlight the requirement to read policy in conjunction with others.

MM60 Comment

Page 127

Para/Table/Box/Policy

E3 (above paragraph 7.26)

Proposed Modification

Insert additional supporting text before paragraph 7.26 to read:

For the purposes of Policy E3, employment development relates to land or premises used for economic activity falling within Class E (commercial, business and service), Class B2 (general industrial) and Class B8 (storage and distribution) of the Town and Country Planning (Use Classes) Order 1987 (as amended) the same uses covered by the term ‘employment use’ elsewhere in the Plan.

Reason

For clarification on the definition of employment development

MM61 Comment

Page 127

Para/Table/Box/Policy

E3

Proposed Modification

Amend policy text of criterion 2c to read:

c) the existing location poses insurmountable environmental harm or amenity harm which cannot be satisfactorily resolved. The Council will require evidence that the site has not been made deliberately unviable, that marketing has been actively conducted for a reasonable period of time and that alternative employment uses have been fully explored.

Reason

To improve clarity and remove subjective terminology, ensuring the policy can be applied consistently and effectively.

MM62 Comment

Page 138

Para/Table/Box/Policy

E9

Proposed Modification

Amend policy text to read:

Policy E9 – Caravans, camping, lodges, log cabins, chalets and similar forms of self-serviced holiday accommodation

In areas outside the Rutland Water Area and the Eyebrook Reservoir Area, Caravans, Camping, Lodges, Log Cabins, Chalets and other similar forms of self-serviced holiday accommodation will only be acceptable where all of the following criteria are met:.......

Reason

Consequential change so that caravanning and camping policy applies throughout the county.

MM63 Comment

Page 141

Para/Table/Box/Policy

7.76

Proposed Modification

Amend paragraph 7.76 to read:

There is very limited quantitative ‘need’ for new convenience goods floorspace, with a requirement up to 2041 of approximately 1,000 sqm net additional convenience floorspace over the new Local Plan period. There is only one supermarket in Uppingham; as such, there is scope to improve choice in the town, with identified need being directed towards strengthening convenience shopping provision within Uppingham to reduce leakage of expenditure to larger centres and to support more sustainable patterns of shopping. The Uppingham Neighbourhood Plan responds directly to this identified need through the allocation of land at Uppingham Gate (Policy U-HA3) for a new retail convenience store, providing an opportunity to enhance local provision, retain spend within the town, and reinforce Uppingham’s role as a key service centre.

Reason

To ensure the Plan accurately reflects adopted neighbourhood planning policy and recognises the local response to identified convenience‑retail need in Uppingham

MM64 Comment

Page 143

Para/Table/Box/Policy

7.88

Proposed Modification

Amend paragraph 7.88 to read:

Policy E10 will ensure new retail development will beis directed to the Oakham and Uppingham town centre areas, allowing it totheir continued development and strengtheningitstheir roles as the principal comparison- shopping destinations in the County. A variety of town centre uses will be encouraged, including food and drink, leisure, and cultural uses that add to the liveliness, attractiveness, and economic resilience of the centre.

Reason

To ensure consistency across the Plan by recognising both Oakham and Uppingham as the County’s two town centres and aligning the supporting text with policy intent for directing retail development.

For instructions on how to use the system and make comments, please see our help guide.