MM29
Representation ID: 9217
Received: 04/09/2026
Respondent: Class Q Ltd
MM29 would insert the
Council’s housing land supply calculation, including a claimed post-adoption five-year supply of 1,203 dwellings, equivalent to 8.2 years.
Class Q objects because RCC9 no longer provides a reliable basis for the proposed Main Modifications. Its completion forecast has been superseded and the published evidence does not demonstrate that the assumed completions from a substantial number of major outline and allocated sites will occur within the five-year period. The Council’s July 2026 assessment adds weight to that concern because it revises a number of the contributions previously included in RCC9 and relies on further sites whose delivery is also disputed.
Full details of the disputed sites are contained within the full submission document.
Object
Main Modifications Consultation
MM86
Representation ID: 9218
Received: 04/09/2026
Respondent: Class Q Ltd
MM86 would replace Figure 11 and Table 6 with the
updated housing trajectory in RCC9.
Class Q objects because RCC9 no longer provides a reliable basis for the proposed Main Modifications. Its completion forecast has been superseded and the published evidence does not demonstrate that the assumed completions from a substantial number of major outline and allocated sites will occur within the five-year period. The Council’s July 2026 assessment adds weight to that concern because it revises a number of the contributions previously included in RCC9 and relies on further sites whose delivery is also disputed.
Full details of the disputed sites are contained within the full submission document.