Regulation 19 Rutland Local Plan

Search representations

Results for National Grid Electricity Distribution search

New search New search

Support

Regulation 19 Rutland Local Plan

Policy INF1 - Infrastructure and connectivity

Representation ID: 8157

Received: 29/11/2024

Respondent: National Grid Electricity Distribution

Agent: Lucy White Planning

Representation Summary:

Priority should be given to retaining high voltage overhead lines, with design principles integrated into development plans. For sites significantly impacted by overhead lines, early masterplanning and Supplementary Planning Documents are recommended.
LPAs must confirm that adequate capacity exists within the electricity network to support planned developments.

For instructions on how to use the system and make comments, please see our help guide.